Latest News
⚡ POWERtrac Group Successfully Commissions 5MVA, 33kV Substation for Polypack Woven Industries ⚡ POWERtrac Group and Kalpa Electrical Pvt. Ltd. Enter Strategic Distribution and Technology Partnership ⚡ Highlights from the 3rd PSC Expo & Seminar! ⚡ Celebrating the Appointment of Executive Engineer Majadur Rahman Tara! ⚡ স্বনামধন্য কনসালট্যান্টের সঙ্গে সৌজন্য সাক্ষাৎ ⚡ First Work Order of 2025: BBT Project for Ziska Pharmaceutical ⚡ Successful technical seminar with engineers from 12 districts across Bangladesh, under the Khulna Division of the Public Works Department (PWD). ⚡ PROMOTED: Engr. Joy Aditya, the factory head of POWERtrac Group has recently been promoted as DGM. ⚡ We have successfully handed over 1. Compact Sub-Station(X2) 2. 1250 KVA, 33/0.415 KV Sub-Station(X2)... ⚡ We have successfully handed Over Tr-1,Tr-2 Dry Type Transformer Varendra University, Rajshahi ⚡ POWERtrac has successfully completed the Design, Supply, Installation, and Commissioning of 100 KWp .... ⚡ We have successfully handed over 5.5 MVA 33kv and 3.5 MVA, 11kv Substation at ICCL. ⚡ POWERtrac Group Successfully Commissions 5MVA, 33kV Substation for Polypack Woven Industries ⚡ POWERtrac Group and Kalpa Electrical Pvt. Ltd. Enter Strategic Distribution and Technology Partnership ⚡ Highlights from the 3rd PSC Expo & Seminar! ⚡ Celebrating the Appointment of Executive Engineer Majadur Rahman Tara! ⚡ স্বনামধন্য কনসালট্যান্টের সঙ্গে সৌজন্য সাক্ষাৎ ⚡ First Work Order of 2025: BBT Project for Ziska Pharmaceutical ⚡ Successful technical seminar with engineers from 12 districts across Bangladesh, under the Khulna Division of the Public Works Department (PWD). ⚡ PROMOTED: Engr. Joy Aditya, the factory head of POWERtrac Group has recently been promoted as DGM. ⚡ We have successfully handed over 1. Compact Sub-Station(X2) 2. 1250 KVA, 33/0.415 KV Sub-Station(X2)... ⚡ We have successfully handed Over Tr-1,Tr-2 Dry Type Transformer Varendra University, Rajshahi ⚡ POWERtrac has successfully completed the Design, Supply, Installation, and Commissioning of 100 KWp .... ⚡ We have successfully handed over 5.5 MVA 33kv and 3.5 MVA, 11kv Substation at ICCL.

4 × 2000 kVA Integrated Substation & BBT Project

Project Scope & Works Executed

  • Design and implementation of four (4) numbers 2000 kVA Substation Systems
  • Supply and installation of 4 × 2000 kVA Power Transformers for mixed-use facilities
  • Installation of BBT (Bus Bar Trunking) System for efficient and structured power distribution
  • Supply and installation of BUSDUCT Wavepro-A System for high-current transmission
  • Integration of substations with Q Center, Q Hotel, and Q Residences
  • Electrical load distribution planning across commercial, hospitality, and residential blocks
  • Installation of protection, safety, and distribution accessories
  • Complete system installation, testing, commissioning, and final handover

Project Summary

POWERtrac successfully executed a large-scale integrated power infrastructure project for Quality Feeds Ltd., covering Q Center, Q Hotel, and Q Residences. The project featured four 2000 kVA substations combined with a high-capacity BBT and BUSDUCT Wavepro-A system, enabling reliable and efficient power distribution across commercial, hotel, and residential facilities. Designed to handle high electrical loads with minimal losses, the system ensures operational reliability, energy efficiency, and scalability for future expansion. This project stands as a benchmark solution for mixed-use developments requiring robust, safe, and well-engineered electrical infrastructure.